Roadworks on Rogers Drive are under way.
Roadworks on Rogers Drive are under way. Michael Nolan

Current road works you need to know about

SOUTH Burnett Regional Council will continue maintaining roads throughout the South Burnett, with several projects under way during August.

Works are continuing with the concrete footpath on Haly St, Kingaroy between Fisher St and Willowglen St.

In Wattlecamp, crews are working to widen and overlay Wattlecamp Rd.

The first 700 metres of the project are already complete, and works are in progress for the remaining 500 metres of the section.

A realignment is almost complete on the Memerambi Barkers Creek Rd, with the clearing, grubbing and earthworks complete, and the gravel base still in progress.

Maintenance crews are planned to work on the following roads for maintenance grading during August:

  • Neale Rd
  • West Wooroolin Rd
  • East Wooroolin Rd
  • Walkers Rd
  • Old Esk North Rd
  • Old Wondai Rd (north)
  • McAllisters Rd

Resheeting on Coverty Rd and Brooklands Pimpimbudgee Rd are also scheduled before the end of August.

The contract work for Rogers Drive roundabout in Kingaroy is under way, with the earthworks stage now generally complete.

The gravel pavement and concrete construction, as well as the construction of the detour into Rogers Drive are under way.

There is also currently work on the shoulder grading on Memerambi-Gordonbrook Rd.

South Burnett

Severe storms forecast for South Burnett

Severe storms forecast for South Burnett

South Burnett residents are reminded to be storm ready.

Trash walker donates rubbish back to the community

Trash walker donates rubbish back to the community

Much loved rubbish collector gives plastics refund to community.

FORMAL GALLERY: Murgon State High School formal 2018

FORMAL GALLERY: Murgon State High School formal 2018

Gore St looked more like the setting of a Hollywood awards show.

Local Partners